Twin Lakes Proposed Improvements

Project Description

As you may have noticed, No-Wake zones have been enforced at Crystal Lake to prevent degradation of the shoreline. In addition, the Twin Lakes (North and South, part of the same chain of critical water bodies as Crystal Lake) have been known to be prone to flooding. To address these issues the City has developed a set of proposed improvements including: 

  1. Regional Pond Expansion
  2. New South Twin Lake Outlet
  3. Crystal Lake Outlet Modifications

Click on the below image to explore details on the proposed improvements and to see a snapshot of the overall production schedule. 

Contacts

Updates 

October 25 - 31

Click the Construction Update (PDF) for a printable pdf version of this information.

1. Regional Pond 

  • No active construction anticipated in the project area. The contractor will be completing final cleanup items on the project as needed.

2. South Twin Outlet 

See below for more information about about traffic control and access closure.

  • No active construction anticipated in the project area. Contractor will be completing final cleanup items on the project as needed.

3. Crystal Lake Outlet

  • Contractor will be actively working at the site, removing the existing outlet structure and starting to install the new structure
  • During the week of Nov 1 - 7, contractor will be continuing work on the outlet structure. Material deliveries will be on-going through the construction to the boat landing area as well as to the active work zone.