Southwest Area (2020)

This Project Includes

Rehabilitation work consisting of replacing the top 2" of pavement and spot replacement of curbs. The following are the areas included in this project:

~ Loop Road North~ Loop Road South
~ Marcia Ann Lane~ Brown Lane
~ Omeara Court~ 152nd St. West
~ Circle High Drive


Contacts

Links

Updates

See phasing map below for reference

Assessment Payments

The interest free pre-payment period for assessments ended on 11/15/2020.  Payments can still be made; however, the total due will now be different as it will include accrued interest.

 

Here are the three payment options:

  • In person at City Hall (open M-F, 8:00am – 4:30pm)
  • Via mail – must be received in our office by 12/15/2020
  • Online until 7:00pm on 12/14/2020

 

Please call for your updated payment amount: Molly at 952-895-4495 or Alicia at 952-895-4534.

August 24, 2020 Update

See updates below by phase.  Click the Construction Update (PDF) for a printable pdf version with additional information.

Loop Road, Marcia Ann Lane, Brown Lane, and Omeara Court

  • Work is complete!

Circle High Drive

  • Mowing and re-seeding has been completed
  • The City and Contractor will be monitoring the boulevards for the next few weeks and may consider a weed and feed application in mid-September 2020, if necessary
Southwest Area Phasing Map