Highland View Area

GovDelivery envelope logo Opens in new windowSubscribe to email updates

Overview

Reconstruction (northern half) consists of complete curb and gutter replacement, roadway reconstruction, water main replacement, storm sewer repairs and upgrades, and sanitary sewer repairs. Reclamation (southern half) consists of replacing all pavement, repairing and/or upgrading storm sewers and sanitary sewers, and spot replacement of curbs.

Notify Us

Click on Notify Us above to tell us about anything on your property or street related to the current projects.

Contacts

Links

Updates

Click on your street segment on the map below or see below for updates.

August 16, 2019

The contractor will be grinding up the remaining asphalt on Phase 2 (Horizon Rd, Horizon Ln, and Horizon Cir) Saturday August 17, 2019.  Grading will continue the week of August 19 until complete.  The contractor is continuing grading in Phase 3 and is tentatively scheduled to place the first layer of asphalt late in the week of August 19.

August 8, 2019

The contractor will be starting grading in Phase 2 the week of August 12.  The contractor will be grinding up the asphalt in phase 3 starting August 13.  Paving the first layer of asphalt in phase 3 is tentatively scheduled for the week of August 26.